<aside> ⚠️ Some orders are delayed and you need to record a delay and extend the order. We record the original end date and the updated end date so you can keep track of orders that were extended.

</aside>

Instructions:

  1. Open up an order that needs to be extended (Find this under the relevant project)
  2. Click on the extend button.

Screenshot 2024-03-07 at 10.14.47 AM.png

  1. Choose the extension end date

Screenshot 2024-03-07 at 10.15.48 AM.png

  1. Click Set Extension

Screenshot 2024-03-07 at 10.15.59 AM.png

  1. The End Date should have changed and the status should be changed to delayed